Tina River Hydropower Project Reaches 23% Completion, Advancing Toward 2028 Commissioning.

Honiara, 28 January 2024 – The Tina River Hydropower Project has achieved a major milestone, with construction now 23% complete as of January 2025. This progress marks a significant step toward delivering affordable, clean, and renewable energy for the Solomon Islands. As one of the country’s largest infrastructure projects, Tina River Hydropower remains on track for completion and commercial operation in early 2028.

Once operational, the 15-megawatt hydropower facility will supply nearly 70% of Honiara’s electricity needs with renewable energy, significantly reducing reliance on costly diesel generation and lowering power prices.

On 28 January 2025, the Tina Hydro Project Office’s Environmental and Safety Team, alongside representatives from the World Bank, conducted a site visit to assess ongoing work. The delegation noted substantial progress compared to the previous year.

According to Hyundai Engineering Company’s Project Manager, Mr. Euiman Moon, overall project completion has reached 23%, with road construction nearing 87% completion. Other critical infrastructure, including dam and powerhouse works, is advancing steadily.

“This milestone underscores our commitment to delivering the project on schedule for commissioning in 2028,” said Mr. Moon. “We continue working closely with Tina Hydropower Limited and the Project Office to ensure construction progresses efficiently while meeting sustainability targets.”

During the site visit, Mr. Moon led the World Bank team on a tour of the dam and powerhouse, highlighting key achievements. With strong collaboration among stakeholders and a steadfast commitment to excellence, the Tina River Hydropower Project is well-positioned to meet its key milestones and deliver lasting benefits to the Solomon Islands.

The Tina River Hydropower Development Project is led by the Solomon Islands Government, with financing and support from the Abu Dhabi Fund for Development, the Asian Development Bank, the Government of Australia, the Green Climate Fund, Korea EX-IM Economic Development Cooperation Fund, and the World Bank.

Caption: Drone footage of construction progress at the Dam site.

CaptionDrone Footage showing the construction of the Box Culvert for diversion of Tina River during construction of the dam.

Caption: HEC Engineers explaining the construction of the tunnel portal to the visiting team.

Caption: Drone Footage of the progress of construction on the Surge Tank and access road to the powerhouse.

For more information, contact:Communications Officer: Jeanine Gadepeta email: jeanine.gadepeta@tina-hydro.com  Tina Hydropower development project  +677 25133 About Tina River Hydro Development Project (TRHDP)

The first large scale renewable energy project for the Solomon Islands delivering benefits such as more affordable electricity and improved accessibility to cleaner, more reliable energy sources for communities now and in the future. It is being implemented by the Solomon Island Government with financing and support from the Abu Dhabi Fund for Development, the Asian Development Bank, the Government of Australia, the Green Climate Fund, Korea EX-IM Economic Development Cooperation Fund, and the World Bank.

Find out more on www.tina-hydro.com

A National Project of Solomon Islands | Tina River Hydropower

Tina River Hydropower is a National Project of Solomon Islands and has as its objective to provide more affordable and reliable energy options to Honiara.

www.tina-hydro.com

or follow us on Facebook | on Instagram |on LinkedIn | on YouTube

Leave a comment